RAMS by job · UK
Cold room installation RAMS
This is a walk-in box plus an F-gas system, not a split on a wall. A cellar-cooling RAMS that never mentions panel fire performance, trapped persons or a first-in alarm will fail a food-factory client.
Typical scope
- Inward escape / alarm before close-up
- Panel handling plan
- Hot-works permit on braze
- F-gas competence on charge
- Hygiene clean
- Emergency release demonstrated
Quick answer
A cold-room installation RAMS covers erecting insulated panels, hanging an evaporator and commissioning a refrigeration system on a named site. Panel handling, refrigerant, and hygiene in a food or pharmacy space dominate.
Primary topic: cold room installation rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Split-system RAMS reused
No panels, no trap risk.
Door closer last, box used as a store
Someone shut in.
Charge by feel
No competence.
Example
Butchery cold room at a market unit
Built from one job description. You review and adjust every item before issuing it.
Job description
Erect a 4 × 3 m cold room at Kirkgate Unit 12, Leeds. Panel system as specified, inward release fitted before the last wall, hot-works on the Saturday, F-gas charge, hygiene clean, market open around the unit, no public in the doorway.
Activities identified
- General site work
- Refrigerant handling
- Manual handling
- Occupied premises or public areas
Method (11 steps)
- 1.Arrive and sign in. Arrive at Unit 12, Kirkgate Market, Leeds, report to the Kirkgate Butchery site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
- 4.Recover refrigerant. Recover the refrigerant into a correctly rated, labelled recovery cylinder. Record quantities in line with F-gas requirements.
- 5.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 7.Pressure test and evacuate. Pressure test with oxygen-free nitrogen, then evacuate the system before charging.
- 8.Charge the system. Charge the system with refrigerant to the manufacturer's specification and leak test all joints.
- 9.Test and commission. Test and commission the installation. Record results.
- 10.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 11.Hand over and sign out. Hand over to the Kirkgate Butchery site contact, report anything outstanding and sign out.
Main risks (4 in total)
Refrigerant release
Residual LowWho: Engineers, building occupants
- Refrigerant handled only by F-gas certified engineers
- Refrigerant recovered into correctly rated, labelled recovery cylinders — never vented
- Good ventilation; no recovery work in enclosed spaces without assessment
- No ignition sources near flammable (A2L/A3) refrigerants; leak detector in use
- Cryogenic-rated gloves and eye protection when connecting hoses
Stored pressure
Residual LowWho: Engineers
- Systems depressurised and drained down before breaking into pipework
- Gauges, hoses and valves inspected and rated for the system pressure
- Cylinders secured upright and transported with valves protected
- Eye protection worn when connecting or venting
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Members of the public and building occupants
Residual LowWho: Public, customers, staff, residents
- Work area segregated with barriers and clear signage
- Work timed for quieter periods where possible, agreed with the site
- Tools and materials never left unattended in public areas
- Site contact informed of work areas and any disruption
What to get right on this document
The door is life safety
Inside release before you close the box.
Panels are a lift
Wind and a stacking plan.
Charge is competence
Named F-gas person.
What this document has to cover
This is a walk-in box plus an F-gas system, not a split on a wall. A cellar-cooling RAMS that never mentions panel fire performance, trapped persons or a first-in alarm will fail a food-factory client.
A cold room installation rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Crushing and cuts from large insulated panels
- Refrigerant release during charge or braze
- Person trapped in a room whose door closer is not yet set
- Hot works on pipework in a panel box
- Hygiene contamination of a food room
- Manual handling of evaporators at height inside the box
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Agree the panel system, fire performance and a door that can be opened from inside before the box is closed
- Handle panels with a plan; stand them safely — no unsecured stacks
- Erect, floor, and hang the evaporator from designed supports
- Pipe, braze under a hot-works permit, pressure-test, charge with competence
- Commission temperature, door heater and the trapped-person alarm
- Clean to the hygiene standard; hand over emergency release
Occupancy and other people
Food factories and hospital pharmacies stay in production next door. Write hygiene zoning and that you do not walk from a yard into an open food room.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Refrigerant (name the actual)
- Panel adhesives and sealants
- Brazing gases and flux
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer cold room installation rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeHVAC RAMSCreate HVAC and refrigeration RAMS online: rooftop units, split systems, refrigerant recovery and brazing. Suggested risks and method steps you review before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this the same as a cellar cooler?
- Cellars are often through-wall units; a cold room is a panel box with a trap risk.
- Fire of PIR panels?
- Use the specified system; storage of spare panels is a fire load — write it.
- Who tests the alarm?
- You, then the dutyholder — demonstrate it.
- Floor insulation in a doorway?
- A trip and a hygiene joint — detail it.