Cladding remediation RAMS

This is not a decorating job. Temporary fire measures, scaffold/MEWP, and what happens when combustible material is removed must be in the sequence.

Typical scope

  • Temporary fire strategy
  • Resident communications
  • Bay-by-bay close
  • Waste route
  • Access handover
  • Exclusion at ground

Quick answer

A cladding remediation RAMS covers stripping and replacing external wall systems on occupied high-rise or complex buildings. Height, fire strategy during strip, falling materials and public exclusion dominate.

Primary topic: cladding remediation rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Decorators’ RAMS

    No fire strategy.

  • Waste in the stair

    Combustible store in an escape.

  • Open bays overnight

    Weather and fire.

Example

High-rise bay replacement

Built from one job description. You review and adjust every item before issuing it.

Job description

Replace rainscreen on elevations A–B at Harbour Tower, Poole. Resident liaison, compensatory detection, mast climber, waste via designated hoist, bays closed each shift.

Activities identified

  • General site work
  • Mobile tower or scaffold
  • Manual handling
  • Lifting operations
  • Occupied premises or public areas

Method (9 steps)

  1. 1.Arrive and sign in. Arrive at Harbour Tower, Poole, report to the Harbour Tower RTM site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
  4. 4.Erect the tower. PASMA-trained operatives erect the mobile tower to the manufacturer's guide and inspect it before use.
  5. 5.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
  6. 6.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  7. 7.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  8. 8.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  9. 9.Hand over and sign out. Hand over to the Harbour Tower RTM site contact, report anything outstanding and sign out.

Main risks (5 in total)

Fall from tower or scaffold, or collapse

Residual Medium

Who: Operatives, people nearby

  • Mobile towers erected by PASMA-trained persons to the manufacturer's guide
  • Scaffold erected by a competent scaffolder and tagged/inspected before use and every 7 days
  • Guard rails, toe boards and brick guards in place on working platforms
  • Castors locked and outriggers fitted; never moved while occupied

Falling objects

Residual Low

Who: People below, other trades, public

  • Exclusion zone set up below the work area with barriers and signage
  • Tools tethered when working at height; materials kept away from edges
  • Banksman or second person controls the area during lifts and removals
  • Hard hats worn in the exclusion zone

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

Lifting operations

Residual Medium

Who: Operatives, public, other trades

  • Lift planned by a competent person; lift plan in place
  • Lifting equipment and accessories have current LOLER thorough examination
  • Exclusion zone below the lift; nobody under suspended loads
  • Trained slinger/signaller directs the lift
  • Lifts stopped in high winds

+ 1 more risks in the full RAMS.

What to get right on this document

Fire in the stripped state

Compensatory measures named.

Residents are occupants

Communications and sterile waste route.

Specified system only

No ‘equivalent’ improvisation.

What this document has to cover

This is not a decorating job. Temporary fire measures, scaffold/MEWP, and what happens when combustible material is removed must be in the sequence.

A cladding remediation rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Falls from height
  • Fire during a partially stripped facade
  • Falling panels and fixings
  • Manual handling and crane interface
  • Public at the building perimeter
  • Existing ACM/MCP unidentified materials

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm the fire strategy for the stripped state and compensatory measures
  • Access and exclusion agreed, including below
  • Strip in planned bays, bag and remove waste on the day
  • Install the specified system only
  • Close the bay weathertight as you go
  • Handover inspections and remaining defects

Occupancy and other people

Residents stay in the building. Lifts, firefighting stairs and a sterile route for waste have to be written, not assumed.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Existing coatings
  • Insulation (possibly combustible waste)
  • Sealants

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer cladding remediation rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this licensed asbestos work?
Only if ACMs are identified — surveys first, do not guess in the RAMS.
Do I need a separate fire RAMS?
The temporary fire strategy belongs here or as an attached plan.
Can I store panels on balconies?
Usually no — write the storage area.
Who inspects the access?
Named, with handover before your first shift.