Chimney stack rebuild RAMS

This is not pointing from a ladder. You are dismantling a structure over a live roof and often a pavement. A generic roofing RAMS about felt and eaves is the wrong document.

Typical scope

  • Scaffold to the stack
  • Exclusion below
  • Other flues isolated or protected
  • Hoist for waste
  • Same-day weather
  • Occupier told before relight

Quick answer

A chimney rebuild RAMS covers striking and rebuilding a stack on a pitched roof. Height, falling masonry, temporary support of remaining flues, and the public below are the core.

Primary topic: chimney rebuild rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Ladder and a bag of mix

    No access or exclusion.

  • Pots rolled down the pitch

    No hoist.

  • Neighbour’s fire still lighting

    Live flue in a struck stack.

Example

Front stack over a pavement

Built from one job description. You review and adjust every item before issuing it.

Job description

Rebuild the front chimney at 2 Cathedral View, Durham. Independent scaffold, pavement licence, hoist, neighbour’s rear flue staying live, lead flashings, occupier not to light the fire until signed back.

Activities identified

  • General site work
  • Mobile tower or scaffold
  • Lifting operations

Method (6 steps)

  1. 1.Arrive and sign in. Arrive at 2 Cathedral View, Durham, report to the Cathedral View Trust site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Erect the tower. PASMA-trained operatives erect the mobile tower to the manufacturer's guide and inspect it before use.
  4. 4.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
  5. 5.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  6. 6.Hand over and sign out. Hand over to the Cathedral View Trust site contact, report anything outstanding and sign out.

Main risks (3 in total)

Fall from tower or scaffold, or collapse

Residual Medium

Who: Operatives, people nearby

  • Mobile towers erected by PASMA-trained persons to the manufacturer's guide
  • Scaffold erected by a competent scaffolder and tagged/inspected before use and every 7 days
  • Guard rails, toe boards and brick guards in place on working platforms
  • Castors locked and outriggers fitted; never moved while occupied

Falling objects

Residual Low

Who: People below, other trades, public

  • Exclusion zone set up below the work area with barriers and signage
  • Tools tethered when working at height; materials kept away from edges
  • Banksman or second person controls the area during lifts and removals
  • Hard hats worn in the exclusion zone

Lifting operations

Residual Medium

Who: Operatives, public, other trades

  • Lift planned by a competent person; lift plan in place
  • Lifting equipment and accessories have current LOLER thorough examination
  • Exclusion zone below the lift; nobody under suspended loads
  • Trained slinger/signaller directs the lift
  • Lifts stopped in high winds

What to get right on this document

Get to the stack safely

Scaffold designed for striking, not a roof ladder.

Below is the public

Licence and exclusion.

Relight is a step

Do not leave appliances unsafe.

What this document has to cover

This is not pointing from a ladder. You are dismantling a structure over a live roof and often a pavement. A generic roofing RAMS about felt and eaves is the wrong document.

A chimney rebuild rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Falls from the scaffold or through the roof
  • Masonry and pots falling into gardens or the highway
  • Collapse of a partly struck stack
  • Leadwork and flashing hot works if used
  • Possible asbestos in old flaunching or bird guards
  • Combustion products if other flues stay live

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm access, exclusion below, and whether other flues must be isolated
  • Strike in planned lifts; load-out via hoist, not over the eaves
  • Rebuild to the design, flaunch, pot and terminals
  • Flash and weather the same day you open the roof
  • Flue test or notice to the occupier before lighting appliances
  • Clear gutters of mortar and remove waste

Occupancy and other people

Terraces sit on pavements and shared roofs. Exclusion, neighbour chimneys still in use, and access for the fire service along the street all belong in the RAMS.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Mortar and cement
  • Lead (if dressing)
  • Possible asbestos in old flaunching — survey first

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer chimney rebuild rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Do I need a flue liner RAMS too?
If you are lining, add that method — combustion and solvents differ.
Hot works for lead?
If you use heat, add a permit; many details are cold-dressed.
Bats in the stack?
Wildlife surveys sit with the client; do not strike if outstanding.
Can I work off the roof ladder?
Not as the main platform for a rebuild.