Cellar cooling RAMS

A cellar is a tight, wet, often occupied store with a hatch people still use. A split-system RAMS that never mentions the hatch, CO2 from cellar gases or how deliveries continue will miss the job.

Typical scope

  • Hatch closed when not passing
  • Delivery freeze agreed
  • Outdoor unit handling
  • Condensate routed
  • F-gas competence
  • Beer-drop kept clear

Quick answer

A cellar-cooling RAMS covers installing a cellar or bottle-store cooler: indoor unit, outdoor condensing unit, pipework and condensate in a pub or hotel. Access through a trap door, refrigerant and beer-drop occupancy are the usual harms.

Primary topic: cellar cooling rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Office split RAMS reused

    No hatch, no barrels.

  • Hatch left open behind a chair

    A fall into the cellar.

  • Outdoor unit on the pavement unbolted

    Public interface.

Example

Cellar cooler through a trap in a trading pub

Built from one job description. You review and adjust every item before issuing it.

Job description

Install a cellar cooler at The Anchor, Whitby. Monday 08:00–16:00, hatch attended or closed, no barrel drop, outdoor unit on the yard wall not the pavement, F-gas charge, condensate to the foul, manager briefed.

Activities identified

  • General site work
  • Refrigerant handling
  • Manual handling
  • Outdoor or exposed work

Method (10 steps)

  1. 1.Arrive and sign in. Arrive at The Anchor, Whitby, report to the The Anchor site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Recover refrigerant. Recover the refrigerant into a correctly rated, labelled recovery cylinder. Record quantities in line with F-gas requirements.
  4. 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  5. 5.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  6. 6.Pressure test and evacuate. Pressure test with oxygen-free nitrogen, then evacuate the system before charging.
  7. 7.Charge the system. Charge the system with refrigerant to the manufacturer's specification and leak test all joints.
  8. 8.Test and commission. Test and commission the installation. Record results.
  9. 9.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  10. 10.Hand over and sign out. Hand over to the The Anchor site contact, report anything outstanding and sign out.

Main risks (4 in total)

Refrigerant release

Residual Low

Who: Engineers, building occupants

  • Refrigerant handled only by F-gas certified engineers
  • Refrigerant recovered into correctly rated, labelled recovery cylinders — never vented
  • Good ventilation; no recovery work in enclosed spaces without assessment
  • No ignition sources near flammable (A2L/A3) refrigerants; leak detector in use
  • Cryogenic-rated gloves and eye protection when connecting hoses

Stored pressure

Residual Low

Who: Engineers

  • Systems depressurised and drained down before breaking into pipework
  • Gauges, hoses and valves inspected and rated for the system pressure
  • Cylinders secured upright and transported with valves protected
  • Eye protection worn when connecting or venting

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

Adverse weather

Residual Low

Who: Operatives

  • Forecast checked before work; work at height stopped in high winds
  • Breaks, water and shade in hot weather; warm clothing in cold
  • Sun protection on exposed work in summer

What to get right on this document

The hatch is the hazard

Closed or attended.

Deliveries are occupancy

Stop them or marshal.

Condensate is not a drip on kegs

Route it.

What this document has to cover

A cellar is a tight, wet, often occupied store with a hatch people still use. A split-system RAMS that never mentions the hatch, CO2 from cellar gases or how deliveries continue will miss the job.

A cellar cooling rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Falls through an open cellar hatch
  • Refrigerant in a poorly ventilated cellar
  • Manual handling of a condensing unit on a yard
  • Electric shock in a wet cellar
  • CO2 or beer-gas cylinders in the same space
  • Staff using the hatch as a stair while you work

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Agree hatch management and whether deliveries are stopped
  • Isolate power; survey the outdoor position and public interface
  • Place the outdoor unit with a handling plan; run pipework the designed route
  • Install the indoor unit; do not block the beer-drop or escape
  • Charge and commission; prove the condensate route
  • Close the hatch whenever you are not passing; brief the manager

Occupancy and other people

Pubs still take barrels. Write the closed hatch, the lookout, and that you do not leave a hole in the bar floor over a Friday night.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Refrigerant
  • Cellar cleaner residues
  • Brazing gases if used

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer cellar cooling rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is cellar CO2 part of this?
If cylinders are in the room, keep valves closed and ventilate; a leak RAMS is separate.
Can I reuse a split-system RAMS?
Only if you add hatch, wet floor and delivery controls — better to use this one.
Listed pub walls?
Do not chase a listed wall without the client’s consent.
Who owns the outdoor unit keys?
The manager — anti-theft and isolation.