Car-park jet fan RAMS

This is not a smoke extract fan RAMS. This job covers installing or replacing jet fans in an occupied or trading car park, and the control that keeps people safe is isolation of the fan circuit and a closed-lane plan before anyone works at height. If the RAMS never names which lanes close, the CO/smoke strategy and how remaining cars circulate, a principal contractor will send it back.

Typical scope

  • Closed-lane plan
  • Fans proved dead
  • MEWP exclusion
  • Strategy returned to auto
  • CO/smoke status written
  • Operator walk

Quick answer

A car park jet fan rams covers installing or replacing jet fans in an occupied or trading car park on a named UK site. The critical control is isolation of the fan circuit and a closed-lane plan before anyone works at height. Write which lanes close, the CO/smoke strategy and how remaining cars circulate into the sequence — a pack that could describe any smoke extract fan RAMS will not survive a competent review.

Primary topic: car park jet fan rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • smoke extract fan RAMS reused

    No isolation of the fan circuit and a closed-lane plan before anyone works at height.

  • Critical control buried

    Which lanes close, the CO/smoke strategy and how remaining cars circulate belongs in the sequence.

  • Occupancy ignored

    The closed lane letters and that a parent will reverse under the machine.

Example

Car-park jet fan on a named site

Built from one job description. You review and adjust every item before issuing it.

Job description

Installing or replacing jet fans in an occupied or trading car park at Level -1, Kennet Deck, Reading. Tuesday 21:00–05:30, trading 07:00. Isolation of the fan circuit and a closed-lane plan before anyone works at height; which lanes close, the CO/smoke strategy and how remaining cars circulate; the closed lane letters and that a parent will reverse under the machine.

Activities identified

  • General site work
  • Electrical isolation
  • Manual handling
  • Plant and vehicle movement
  • Occupied premises or public areas
  • Outdoor or exposed work

Method (10 steps)

  1. 1.Arrive and sign in. Arrive at Level -1, Kennet Deck, Reading, report to the Kennet Property Services site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
  4. 4.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
  5. 5.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  6. 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  7. 7.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
  8. 8.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
  9. 9.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  10. 10.Hand over and sign out. Hand over to the Kennet Property Services site contact, report anything outstanding and sign out.

Main risks (5 in total)

Electric shock or burns

Residual Medium

Who: Operatives, building occupants

  • Work carried out dead — no live working
  • Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
  • Only competent, qualified electricians carry out electrical work
  • Permit to work obtained where the site requires one
  • Personal locks and keys retained by the person working

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

Moving vehicles and plant

Residual Medium

Who: Operatives, public, site staff

  • Pedestrians segregated from vehicle and plant routes
  • Plant operated by trained, authorised operators only
  • Banksman used for reversing and manoeuvring
  • High-visibility clothing worn

Members of the public and building occupants

Residual Low

Who: Public, customers, staff, residents

  • Work area segregated with barriers and clear signage
  • Work timed for quieter periods where possible, agreed with the site
  • Tools and materials never left unattended in public areas
  • Site contact informed of work areas and any disruption

+ 1 more risks in the full RAMS.

What to get right on this document

Critical control first

Put this hold point first: isolation of the fan circuit and a closed-lane plan before anyone works at height.

Name the site facts

Which lanes close, the CO/smoke strategy and how remaining cars circulate

People who did not read the pack

Retail parks stay busy

What this document has to cover

This is not a smoke extract fan RAMS. This job covers installing or replacing jet fans in an occupied or trading car park, and the control that keeps people safe is isolation of the fan circuit and a closed-lane plan before anyone works at height. If the RAMS never names which lanes close, the CO/smoke strategy and how remaining cars circulate, a principal contractor will send it back.

A car park jet fan rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Fall from a MEWP onto a circulating lane
  • Electric shock on a fan that shares a smoke-control board
  • Cars entering a closed bay
  • Dropped fans crushing people or vehicles
  • CO build-up if too many fans are off in a live park
  • Fire-strategy fan left in hand after the visit

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Agree closed lanes and remaining ventilation with the operator
  • Isolate and prove dead the named fans
  • MEWP exclusion; banksman for circulating cars
  • Land and terminate; label fire-strategy status
  • Commission and return fans to auto
  • Operator walk before reopen

Occupancy and other people

Retail parks stay busy. Write the closed lane letters and that a parent will reverse under the machine as occupancy control, not a hope.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Cleaning wipes
  • Paint on hangers
  • Dust from the soffit

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer car park jet fan rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this a smoke-extract fan job?
Related kit. A jet fan in a trading park adds circulating cars and a CO strategy.
Can one lane stay open?
Yes if the exclusion holds — write the letters.
Who owns fire-strategy status?
The operator. Hand mode is a defect.
CO while fans are off?
Write remaining ventilation or a closed park.