Cable containment RAMS

Containment is the structure cables will sit on for twenty years. A lighting RAMS that never mentions hanger load, fire-stopping of tray penetrations or how you cut in an occupied corridor is the wrong document.

Typical scope

  • Hanger centres as drawn
  • Cutting bay
  • Fire-stop same visit
  • Escape kept clear
  • Swarf catch below
  • Sharp ends capped

Quick answer

A cable containment RAMS covers fixing tray, basket, ladder or trunking on a named route. Height in voids, cutting swarf, and not overloading hangers are the usual controls a ‘first-fix electric’ paragraph skips.

Primary topic: cable containment rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Cable-pull RAMS reused

    No hangers, no fire-stop.

  • Angle grinder in the aisle

    Swarf on laptops.

  • Slot left in a compartment wall

    Fire strategy open.

Example

Level-3 basket run out of hours

Built from one job description. You review and adjust every item before issuing it.

Job description

Install basket containment on level 3 at Civic House, York. 20:00–06:00, podiums, cutting bay in the loading dock, fire-stop at the stair wall the same night, swarf sheets under the grid, corridor kept as an escape.

Activities identified

  • General site work
  • Ladders or stepladders
  • Manual handling
  • Power tools
  • Lone working

Method (8 steps)

  1. 1.Arrive and sign in. Arrive at Level 3, Civic House, York, report to the Civic House FM site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up access equipment. Inspect and set up the podium or stepladder on firm, level ground in the work area.
  4. 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  5. 5.Drill and fix. Mark out, then drill and fix using on-tool dust extraction. Check for hidden cables and pipes before drilling.
  6. 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  7. 7.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  8. 8.Hand over and sign out. Hand over to the Civic House FM site contact, report anything outstanding and sign out.

Main risks (5 in total)

Fall from ladders or stepladders

Residual Medium

Who: Operatives

  • Use a podium or mobile tower instead of a ladder where the task allows
  • Ladders only for short-duration (under 30 minutes), light work with three points of contact
  • Ladder inspected before use; industrial-grade (EN 131 professional) only
  • Ladder set on firm, level ground and footed or secured
  • No overreaching — move the ladder instead

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

Hand and power tools

Residual Low

Who: Operatives

  • Battery or 110V tools used; no 230V tools on site without RCD protection
  • Tools inspected before use and PAT tested where applicable
  • Guards fitted and used as designed
  • Eye protection and gloves suitable for the task

Noise and hand-arm vibration

Residual Medium

Who: Operatives, people nearby

  • Low-vibration, low-noise tools selected
  • Trigger times limited and rotated between operatives
  • Noisy work scheduled to reduce disruption to occupants
  • Hearing protection worn where noise is high

+ 1 more risks in the full RAMS.

What to get right on this document

Hangers are the job

Centres and fixings, not hope.

Cut away from people

A bay, not the desk line.

Close the compartment

Fire-stop before you leave.

What this document has to cover

Containment is the structure cables will sit on for twenty years. A lighting RAMS that never mentions hanger load, fire-stopping of tray penetrations or how you cut in an occupied corridor is the wrong document.

A cable containment rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Falls from podiums and towers in ceiling voids
  • Cuts from freshly sheared tray and falling off-cuts
  • Manual handling of 3 m ladder lengths in stairs
  • Overloading hangers or using the wrong fixings in a fire-rated slab
  • Fire-stopping left open where tray crosses a compartment
  • Swarf in eyes and on occupied desks below an open grid

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm route, hanger centres and fire-compartment crossings from the drawings
  • Protect occupied rooms; set access that leaves an escape
  • Fix hangers, land containment, cut only in a designated bay with eye protection
  • Fire-stop every penetration the same visit — do not leave a slot
  • Cap sharp ends and drop waste via the planned route, not through a grid
  • Hand over residual load capacity and remaining open ends

Occupancy and other people

Live offices will sit under an open ceiling. Catch swarf, keep the corridor passable, and do not use the tea-point as a cutting bench.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Cutting fluid if used
  • Fire-stopping mastics at penetrations
  • Galvanising touch-up aerosol

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer cable containment rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this the same as pulling cables?
Pulling comes later. This RAMS is the metal the cables sit on.
Can I sit on the tray?
No — it is not a platform. Write access separately.
Heavy ladder vs basket?
Ladder needs a handling and hanger-load plan; do not copy basket text.
Who signs the fire-stop?
Usually the fire package or clerk of works — photograph and label it.