Brickwork and pointing RAMS

Pointing from a ladder over a shopfront is how people get hurt. A generic construction RAMS that never mentions raking dust, mortar COSHH or pavement exclusion is not site-specific.

Typical scope

  • Access inspected
  • Public exclusion
  • Dust control on mechanical rake
  • Cement COSHH
  • Frost abort
  • Waste not over the edge

Quick answer

A brickwork and pointing RAMS covers laying or raking and pointing masonry on a named elevation. Height, cement, silica if grinding joints, and the public below are the usual harms.

Primary topic: brickwork pointing rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Ladder and a hawk

    No platform or exclusion.

  • Angle grinder dry on joints

    Silica.

  • Mix on the pavement

    Trip and cement in the gulley.

Example

Front-elevation pointing over a shop

Built from one job description. You review and adjust every item before issuing it.

Job description

Rake and point the first-floor brickwork at 22 High Street, Chester. Tower, pavement licence, M-class extract on the rake, cement COSHH, shop remaining open, no work in frost, waste in tubs.

Activities identified

  • General site work
  • Mobile tower or scaffold
  • Dust-generating work
  • Occupied premises or public areas
  • Using chemicals or products

Method (7 steps)

  1. 1.Arrive and sign in. Arrive at 22 High Street, Chester, report to the High Street Retail Ltd site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
  4. 4.Erect the tower. PASMA-trained operatives erect the mobile tower to the manufacturer's guide and inspect it before use.
  5. 5.Apply products. Apply products as described on the Safety Data Sheet and COSHH assessment, with ventilation and the specified PPE.
  6. 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  7. 7.Hand over and sign out. Hand over to the High Street Retail Ltd site contact, report anything outstanding and sign out.

Main risks (5 in total)

Fall from tower or scaffold, or collapse

Residual Medium

Who: Operatives, people nearby

  • Mobile towers erected by PASMA-trained persons to the manufacturer's guide
  • Scaffold erected by a competent scaffolder and tagged/inspected before use and every 7 days
  • Guard rails, toe boards and brick guards in place on working platforms
  • Castors locked and outriggers fitted; never moved while occupied

Falling objects

Residual Low

Who: People below, other trades, public

  • Exclusion zone set up below the work area with barriers and signage
  • Tools tethered when working at height; materials kept away from edges
  • Banksman or second person controls the area during lifts and removals
  • Hard hats worn in the exclusion zone

Dust (including silica)

Residual Medium

Who: Operatives, people nearby

  • Use pre-formed holes, or methods that create less dust
  • On-tool extraction (M- or H-class) or water suppression when cutting or drilling
  • Clean up with an M-class vacuum — no dry sweeping
  • Face-fit tested RPE (FFP3 or equivalent) worn

Members of the public and building occupants

Residual Low

Who: Public, customers, staff, residents

  • Work area segregated with barriers and clear signage
  • Work timed for quieter periods where possible, agreed with the site
  • Tools and materials never left unattended in public areas
  • Site contact informed of work areas and any disruption

+ 1 more risks in the full RAMS.

What to get right on this document

Get a platform

Pointing is height work.

If you grind, extract

Silica is the harm.

Below is the public

Sheeting and a lookout.

What this document has to cover

Pointing from a ladder over a shopfront is how people get hurt. A generic construction RAMS that never mentions raking dust, mortar COSHH or pavement exclusion is not site-specific.

A brickwork pointing rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Falls from scaffold, tower or MEWP
  • Cement burns and dermatitis
  • Silica from mechanical raking or grinding
  • Falling mortar and tools onto the public
  • Manual handling of packs and mix
  • Weather — frost on mortar, wind on the platform

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Inspect access and set exclusion / sheeting below
  • Rake or grind only with dust control if mechanical
  • Mix in a bay, apply mortar, tool joints
  • Protect fresh work from frost and rain
  • Drop waste via chute or tubs, not over the edge
  • Wash splash off the pavement and hand over

Occupancy and other people

Shopfronts and school playgrounds stay open. A mortar drop on a pram is a RAMS failure. Write the lookout and the hours around pick-up.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Mortar and cement
  • Lime if used
  • Silica dust if grinding joints

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer brickwork pointing rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Lime mortar?
Different COSHH and weather windows — write the mix.
Is grinding always required?
Often a plug cutter or hand rake is enough and better for silica.
Do I need a scaffold RAMS too?
Your user RAMS sits with the access handover.
Salt in the wall?
A specification issue; do not wash salts into the street drain as a method.