Booster set installation RAMS
A booster is a live water machine with stored energy in vessels. A general plumbing RAMS that never mentions the lift, a burst during commission or how the upper floors stay supplied will fail the FM.
Typical scope
- Outage and lift plan
- Controlled drain
- Design pressures
- Hygiene flush
- Leak check at duty pressure
- Vessel pre-charge recorded
Quick answer
A booster-set RAMS covers placing, pipework and commissioning a cold-water booster package. Lifting the skid, isolation of the incoming main, noise in a plant room and not leaving the building without water are the critical controls.
Primary topic: booster set installation rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Pump swap RAMS reused
No vessels, no outage plan.
Started against a closed valve
Burst.
Top-floor kitchen left dry with no warning
Occupancy.
Example
Basement booster for a student block
Built from one job description. You review and adjust every item before issuing it.
Job description
Install a twin booster at Castle Gate Residences, Newcastle. Saturday hoist through the lightwell, incoming isolated 08:00–16:00, bottled water on floors 4–6, design duty 3.8 bar, flush record, warden briefed before start-up.
Activities identified
- General site work
- Manual handling
- Lifting operations
Method (7 steps)
- 1.Arrive and sign in. Arrive at Basement plant, Castle Gate Residences, Newcastle, report to the Castle Gate Residences site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
- 4.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 5.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 6.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 7.Hand over and sign out. Hand over to the Castle Gate Residences site contact, report anything outstanding and sign out.
Main risks (2 in total)
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Lifting operations
Residual MediumWho: Operatives, public, other trades
- Lift planned by a competent person; lift plan in place
- Lifting equipment and accessories have current LOLER thorough examination
- Exclusion zone below the lift; nobody under suspended loads
- Trained slinger/signaller directs the lift
- Lifts stopped in high winds
What to get right on this document
Water is occupancy
Who loses it, for how long.
Pressures are designed
Not a guess on the gauge.
Flush is hygiene
Do not hand over a stagnant set.
What this document has to cover
A booster is a live water machine with stored energy in vessels. A general plumbing RAMS that never mentions the lift, a burst during commission or how the upper floors stay supplied will fail the FM.
A booster set installation rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Dropped skid in a basement plant room
- Burst or water damage on first start
- Electric shock on the package isolator
- Noise and vibration into occupied rooms above
- Legionella if a vessel or loop is left stagnant
- Building without water because both duty and standby were isolated
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Agree the water outage and a lift plan for the skid
- Isolate incoming and downstream; drain to a controlled point
- Land the set, inertia bases if specified, pipe and electrical connections
- Fill, vent, set pressures to the design — not ‘until it looks right’
- Commission changeover; check for leaks at running pressure
- Hand over isolation, vessel pre-charge and the hygiene flush record
Occupancy and other people
Blocks and hotels cannot lose water over a weekend without a plan. Write bottled water or a temporary feed if the outage is long, and who is told on the top floor.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Water treatment / inhibitors if dosed
- Glycol only if a combined set
- Cleaning chemicals on a dirty old set
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer booster set installation rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradePlumbing RAMSCreate plumbing and heating RAMS online: boiler swaps, pipework, unvented cylinders and drain-downs. Suggested risks and method steps, reviewed by you.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsPlumbing method statementWrite a plumbing method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is this the same as a pressurisation unit?
- No — boosters raise cold water; pressurisation units hold sealed heating systems.
- Do I need a break tank RAMS too?
- If you are setting a tank, add hygiene and confined access; do not hide it.
- WRAS / water regs?
- Follow the specification; this page is not that determination.
- Who sets the vessel?
- Record pre-charge — it is part of handover.