Attenuation tank RAMS

Attenuation is a designed store with a throttle, not a soakaway. A crate-soakaway RAMS that never mentions the flow-control chamber, lining or how you stop cars driving over an open excavation will fail the drainage engineer.

Typical scope

  • Traffic plan
  • Shoring as designed
  • No unplanned entry
  • Specified outfall only
  • Backfill before cars
  • Throttle setting recorded

Quick answer

An attenuation-tank RAMS covers excavating and installing a storm-water storage tank and flow control on a named site. Collapse, a confined tank, and not leaving a live car park over an unbackfilled hole are the core.

Primary topic: attenuation tank rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • Soakaway RAMS reused

    No throttle, no liner.

  • Cars on plates over a void

    Collapse.

  • Someone in the tank to ‘check the liner’

    No entry plan.

Example

Storm tank under a trading car park

Built from one job description. You review and adjust every item before issuing it.

Job description

Install an attenuation tank under bays 40–52 at Riverside Retail, Preston. Bays closed, scan, shoring, no man-entry, flow-control as drawn, backfill before plates come up, throttle recorded, shoppers marshalled to the east car park.

Activities identified

  • General site work
  • Manual handling
  • Confined space
  • Plant and vehicle movement
  • Occupied premises or public areas
  • Outdoor or exposed work

Method (8 steps)

  1. 1.Arrive and sign in. Arrive at Riverside Retail, Preston, report to the Riverside Retail FM site contact, sign in and complete any site induction.
  2. 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
  3. 3.Set up the work area. Set up barriers and signage around the work area and keep it clear of other people.
  4. 4.Confined space permit and gas test. Obtain the permit to work, test the atmosphere and confirm rescue arrangements before anyone enters.
  5. 5.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
  6. 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
  7. 7.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
  8. 8.Hand over and sign out. Hand over to the Riverside Retail FM site contact, report anything outstanding and sign out.

Main risks (5 in total)

Manual handling

Residual Medium

Who: Operatives

  • Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
  • Team lifts for items too heavy or awkward for one person
  • Route planned and cleared before moving items
  • Operatives trained in safe lifting techniques
  • Gloves with good grip and safety footwear

Confined space

Residual Medium

Who: Operatives, rescuers

  • Avoid entry — do the work from outside where possible
  • Permit to work and confined space trained operatives
  • Atmosphere tested before and during entry with a calibrated gas monitor
  • Emergency rescue arrangements in place before entry

Moving vehicles and plant

Residual Medium

Who: Operatives, public, site staff

  • Pedestrians segregated from vehicle and plant routes
  • Plant operated by trained, authorised operators only
  • Banksman used for reversing and manoeuvring
  • High-visibility clothing worn

Members of the public and building occupants

Residual Low

Who: Public, customers, staff, residents

  • Work area segregated with barriers and clear signage
  • Work timed for quieter periods where possible, agreed with the site
  • Tools and materials never left unattended in public areas
  • Site contact informed of work areas and any disruption

+ 1 more risks in the full RAMS.

What to get right on this document

The throttle is the job

Record the setting.

Cars wait

Backfill first.

Tanks are confined spaces

Do not drop in.

What this document has to cover

Attenuation is a designed store with a throttle, not a soakaway. A crate-soakaway RAMS that never mentions the flow-control chamber, lining or how you stop cars driving over an open excavation will fail the drainage engineer.

An attenuation tank rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • Excavation collapse on a deep tank
  • Confined entry into the tank or chamber
  • Services in a car-park slab
  • Cars or plant over an unbackfilled tank
  • Pollution if you connect foul or a wrong outfall
  • Lifting heavy lids and crates

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • Confirm the design, outfall and a temporary traffic plan before the slab is cut
  • Shoring as designed; CAT and scan the deck
  • Install tank, liner if specified, and the flow-control chamber — do not enter unless planned
  • Connect only the specified storm runs
  • Backfill in layers; do not open the deck to cars until the design allows
  • Lock covers; hand over the throttle setting

Occupancy and other people

Retail parks stay trading. Write the closed bays and that a shopper will park on steel plates if you let them.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Liner adhesives if used
  • Diesel from plant
  • Silt from the excavation

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer attenuation tank rams document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All rams by job · RAMS by trade · Free RAMS generator

Questions

Is this a soakaway?
No — this stores and discharges at a controlled rate.
Who sets the orifice?
The design — do not drill a ‘better’ hole.
Can I enter to joint crates?
Stay topside unless an entry plan, gas and rescue are in force for that tank.
Foul connection nearby?
Keep them separate — a wrong tee is a pollution incident.