RAMS by job · UK
AHU replacement RAMS
AHUs are heavy, dirty and sit on live buildings. A chiller RAMS that never mentions dirty filters, Legionella in humidifiers, or how the floors stay ventilated during the swap is the wrong pack.
Typical scope
- Lift plan
- Ventilation outage plan
- Filter waste as COSHH
- Electrical isolation
- Hygiene on humidifiers
- Commissioning
Quick answer
An AHU replacement RAMS covers swapping an air-handling unit on a roof or in a plant room: lift, isolation of electrics, water and controls, filters and hygiene. The lift and the building remaining ventilated are the usual critical points.
Primary topic: ahu replacement rams. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Chiller RAMS reused
No filters, hygiene or ventilation outage.
Filters emptied over the car park
Dust on the public.
No outage message
Wards wondering why the air stopped.
Example
Roof AHU swap on a live office
Built from one job description. You review and adjust every item before issuing it.
Job description
Replace AHU-2 on the plant deck at Quay House, Bristol. Sunday crane, car-park exclusion, isolate electrical and water, bag filters, temporary ventilation plan for floor 3, commission before Monday 07:00.
Activities identified
- General site work
- Electrical isolation
- Manual handling
- Lifting operations
Method (10 steps)
- 1.Arrive and sign in. Arrive at Quay House, Bristol, report to the Quay Facilities Ltd site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Isolate the electrical supply. Identify the relevant circuit, isolate, lock off and tag. Prove dead with an approved voltage indicator, proved before and after use.
- 4.Carry out the lift. Carry out lifts to the lift plan, with the exclusion zone in place and a trained slinger/signaller directing.
- 5.Disconnect and remove existing equipment. Disconnect and remove the existing equipment. Lower or carry it using mechanical aids or team lifts as planned.
- 6.Install new equipment. Position and fix the new equipment to the manufacturer's instructions.
- 7.Carry out electrical work. Carry out the electrical work on the isolated circuit to BS 7671.
- 8.Remove isolation and re-energise. Confirm the work is complete and everyone is clear, remove locks and re-energise.
- 9.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 10.Hand over and sign out. Hand over to the Quay Facilities Ltd site contact, report anything outstanding and sign out.
Main risks (3 in total)
Electric shock or burns
Residual MediumWho: Operatives, building occupants
- Work carried out dead — no live working
- Safe isolation: isolate, lock off, tag, and prove dead with an approved voltage indicator (GS38) proved before and after
- Only competent, qualified electricians carry out electrical work
- Permit to work obtained where the site requires one
- Personal locks and keys retained by the person working
Manual handling
Residual MediumWho: Operatives
- Use mechanical aids (trolleys, sack trucks, hoists) for heavy items
- Team lifts for items too heavy or awkward for one person
- Route planned and cleared before moving items
- Operatives trained in safe lifting techniques
- Gloves with good grip and safety footwear
Lifting operations
Residual MediumWho: Operatives, public, other trades
- Lift planned by a competent person; lift plan in place
- Lifting equipment and accessories have current LOLER thorough examination
- Exclusion zone below the lift; nobody under suspended loads
- Trained slinger/signaller directs the lift
- Lifts stopped in high winds
What to get right on this document
Occupants need air
Outage window and message.
Filters are waste
Bagged, not shaken.
The lift is planned
Radius and exclusion.
What this document has to cover
AHUs are heavy, dirty and sit on live buildings. A chiller RAMS that never mentions dirty filters, Legionella in humidifiers, or how the floors stay ventilated during the swap is the wrong pack.
An ahu replacement rams only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- Dropped load on a plant-deck lift
- Work at height on decks and in modules
- Electric shock and stored energy in fans
- Hygiene — old filters, microbial growth, humidifier water
- Other trades and the public under a roof lift
- Building occupants losing ventilation or getting construction air
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- Lift plan and a ventilation strategy for the occupied floors during the outage
- Isolate electrical, water, controls and fire-alarm interfaces
- Bag old filters as waste; do not bang them out on the deck
- Lift out, position the new unit, reconnect
- Commission airflow, dampers and any humidifier hygiene
- Remove the old unit and reinstate edge protection
Occupancy and other people
Offices and hospitals need air. Write the outage window, temporary ventilation if required, and who is told on each floor.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- Old filter dust (possible contaminants)
- Coil cleaners
- Glycol or humidifier chemicals if present
- Refrigerant only if the unit is DX
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer ahu replacement rams document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- RAMS by tradeHVAC RAMSCreate HVAC and refrigeration RAMS online: rooftop units, split systems, refrigerant recovery and brazing. Suggested risks and method steps you review before issue.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- Method statementsHVAC installation method statementWrite a hvac installation method statement for a named UK site. Clear sequence, interfaces and controls — review before issue.
- RAMS by jobConsumer unit replacement RAMSCreate a consumer unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEV charger installation RAMSCreate a ev charger installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobLighting rewire RAMSCreate a lighting rewire rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobEICR testing RAMSCreate a eicr method statement for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobRooftop condenser replacement RAMSCreate a rooftop ac unit replacement rams for a named UK site. Suggested risks and method steps you review before download or issue.
- RAMS by jobSplit system installation RAMSCreate a split system installation rams for a named UK site. Suggested risks and method steps you review before download or issue.
Questions
- Is filter dust COSHH?
- Treat used filters as a hazardous task until you know otherwise — especially healthcare.
- DX coil on the AHU?
- Add F-gas recovery; do not skip it because the page says ‘air handling’.
- Can we run on one AHU?
- If the design allows, write that as the occupancy control.
- Legionella in humidifiers?
- Drain, clean and do not leave stagnant water — attach the hygiene scheme.