RAMS vs construction phase plan (CDM)
Submitting a RAMS when the PC asked for input to the CPP — or vice versa — slows the job and looks amateur.
On this page
- CPP = site
- RAMS = package
- PC vs contractor
- Site rules flow down
- Not interchangeable
- CDM roles
Quick answer
A construction phase plan (CPP) is the principal contractor’s plan for the whole site under CDM. A RAMS is usually a contractor’s job-specific risk assessment and method statement. One does not replace the other.
Primary topic: rams vs construction phase plan. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
One document to rule them all
Wrong.
RAMS with a different fire plan
Conflict.
No package RAMS
CPP too high-level.
What to get right on this document
Know who owns which
PC vs you.
Flow down site rules
Into the RAMS.
Don’t paste the CPP
Reference it.
What this document has to cover
Submitting a RAMS when the PC asked for input to the CPP — or vice versa — slows the job and looks amateur.
A rams vs construction phase plan only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.
Typical hazards to assess on this job
- CPP copied from last site
- RAMS pretending to be a CPP
- No RAMS because ‘we have a CPP’
- Trade RAMS that ignore the CPP’s fire plan
Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.
A method sequence that actually protects people
Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.
- PC owns the CPP
- Each contractor supplies RAMS for their package
- CPP sets site rules the RAMS must follow
- Do not duplicate the whole CPP inside every RAMS
Occupancy and other people
Your RAMS assembly point should match the CPP, not your office’s.
Substances and COSHH
An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:
- N/A
How SafeForJob helps
- Describe this job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer rams vs construction phase plan document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- GuidesCDM and RAMS responsibilitiesHow contractors use RAMS under CDM without pretending software assigns legal duties. Practical UK guidance for contractors — with links to free tools.
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- GuidesAre RAMS a legal requirement?Honest UK guidance: risk assessment is required; ‘RAMS’ as a format is how contractors usually record it. Not legal advice.
- GuidesRAMS vs method statementHow the risk assessment and method statement fit together, and when clients ask for a combined RAMS. Practical UK guidance for contractors — with links to free tools.
- GuidesWhat is a COSHH assessment?COSHH assessments explain how you control hazardous substances for a real task, using the SDS. Practical UK guidance for contractors — with links to free tools.
- GuidesSDS vs COSHH assessmentWhy a safety data sheet informs but does not replace your COSHH assessment. Practical UK guidance for contractors — with links to free tools.
- GuidesWorking at height in RAMSHow to describe access equipment, fragile surfaces and rescue thinking inside a RAMS. Practical UK guidance for contractors — with links to free tools.
- GuidesRAMS for occupied premisesExtra controls when residents, staff, patients or customers stay in the building. Practical UK guidance for contractors — with links to free tools.
- GuidesHow to write a RAMSA practical sequence: describe the job, list hazards, choose controls, write the method, check names. Practical UK guidance for contractors — with links to free tools.
Questions
- Do small jobs need a CPP?
- CDM still applies; whether a CPP is required depends on the project — get advice. This page is not that determination.