Keep COSHH beside the RAMS, not in a separate forgotten folder

Clients ask for ‘RAMS and COSHH’. They mean both, together, for this job — not a zip of supplier PDFs.

On this page

  • Substances from the method
  • SDS plus task
  • Process dusts included
  • Attached to the issued pack
  • Briefed together
  • Refreshed on change

Quick answer

COSHH with the RAMS means the task-based assessment travels with the pack the crew is briefed on. The SDS stays an input.

Primary topic: coshh with rams pack. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.

What usually goes wrong

These are the operational gaps that make generic Word RAMS fail on the next site.

  • SDS zip

    Rejected.

  • See COSHH, no file

    Failed brief.

  • No process dusts

    Incomplete.

What to get right on this document

Together is the pack

Not a second folder.

SDS ≠ COSHH

Still.

Process dusts count

No bottle needed.

What this document has to cover

Clients ask for ‘RAMS and COSHH’. They mean both, together, for this job — not a zip of supplier PDFs.

A coshh with rams pack only holds up if it names the site, the people at risk, the critical control, and the order of work. Principal contractors reject paragraphs that could apply to any job of this type.

Typical hazards to assess on this job

  • SDS zip attached, no assessment
  • COSHH for last month’s product
  • Process dusts omitted because there was no can
  • Separate folder nobody briefs
  • Issued RAMS with ‘see COSHH’ and no file
  • US HazCom copied onto a UK pack

Likelihood and severity change with occupancy, access, weather and other trades. Copying last month’s scores without looking at this site is how people get hurt.

A method sequence that actually protects people

Write the sequence so the critical control cannot be skipped. If isolation, edge protection or service location is the difference between safe and unsafe, it belongs before the work step — not in a general ‘PPE will be worn’ line.

  • List substances the method actually uses
  • Assess each from the SDS plus the task
  • Include process dusts you generate
  • Attach assessments to the issued pack
  • Brief both
  • Refresh when the product changes

Occupancy and other people

The people on site breathe this room, not last job’s basement.

Substances and COSHH

An SDS is an input, not a COSHH assessment. If these substances appear on the job, attach assessments that describe quantity, duration, who is exposed and the controls you will actually use:

  • Every hazardous substance in the method
  • Process-generated dusts and fumes

How SafeForJob helps

  • Describe this job in plain English and get suggested activities, risks and method steps
  • Edit every line before you download or issue
  • Reuse a previous RAMS and catch old client or site names
  • Attach or create COSHH assessments where hazardous substances appear

What this page is not

This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer coshh with rams pack document for a named job. You remain responsible for reviewing and issuing it.

Related reading

See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.

Related pages

All guides · RAMS by trade · Free RAMS generator

Questions

Do I always need COSHH with a RAMS?
When the method uses or generates a hazardous substance, assess it and keep it with the pack.
Is an SDS enough to attach?
No.
What about welding fume?
Process-generated — still assess it. See the process-dust guide.
Can the SDS reader issue COSHH?
It helps you read the SDS. You still write the task and review the assessment.