Demolition and strip-out RAMS
Create a site-specific demolition or strip-out RAMS online. Describe the job, review suggested risks and method steps, and download a professional PDF.
Typical scope
- Soft strip
- Internal demolition
- Structural demolition (high-level overview)
- Facade removal prep
- Skip and waste routes
- Live-site strip-out
Never start soft strip without clarity on asbestos and structure. Sequence is a control.
Quick answer
A demolition or soft-strip RAMS must lead with surveys (including asbestos), exclusion, structural sequence, dust/noise and how services are isolated before strip-out begins.
Primary topic: strip out method statement. UK contractors — review every document before you issue it. SafeForJob does not replace competent judgement or HSE guidance.
What usually goes wrong
These are the operational gaps that make generic Word RAMS fail on the next site.
Asbestos survey ignored
Refurb/demolition surveys before disturbance.
Services live
Isolation certificates before strip.
Public interface
Dust, noise and falling materials near boundaries.
Example
Soft strip of a 1980s office floor
Built from one job description. You review and adjust every item before issuing it.
Job description
Soft strip floor 4 at Civic House ahead of Cat-A fit-out. R&D asbestos survey complete, live services capped, temporary dust screens to stair cores, skips in the service yard.
Activities identified
- General site work
- Dust-generating work
- Work in an older building
- Outdoor or exposed work
Method (5 steps)
- 1.Arrive and sign in. Arrive at Civic House, floor 4, report to the Civic House Ltd site contact, sign in and complete any site induction.
- 2.Brief the team. Brief all operatives on this RAMS, the COSHH assessments and the emergency arrangements. Record attendance.
- 3.Check the asbestos register. Check the asbestos register or survey for the work area with the site contact before disturbing any fabric.
- 4.Clear up and remove waste. Clear the work area, remove waste from site (including recovered refrigerant and hazardous waste) and leave the area safe.
- 5.Hand over and sign out. Hand over to the Civic House Ltd site contact, report anything outstanding and sign out.
Main risks (3 in total)
Dust (including silica)
Residual MediumWho: Operatives, people nearby
- Use pre-formed holes, or methods that create less dust
- On-tool extraction (M- or H-class) or water suppression when cutting or drilling
- Clean up with an M-class vacuum — no dry sweeping
- Face-fit tested RPE (FFP3 or equivalent) worn
Disturbing asbestos
Residual MediumWho: Operatives, building occupants
- Asbestos register / refurbishment survey checked for the work area before starting
- Do not drill, cut or disturb suspect materials; stop work and report if found
- Operatives have current asbestos awareness training
Adverse weather
Residual LowWho: Operatives
- Forecast checked before work; work at height stopped in high winds
- Breaks, water and shade in hot weather; warm clothing in cold
- Sun protection on exposed work in summer
What to get right on this document
Surveys first
Asbestos and structural information before methods.
Exclusion and monitoring
Who can enter, when.
Waste routes
Skip locations, segregation, highway licences.
Quick answer
A demolition or soft-strip RAMS must lead with surveys (including asbestos), exclusion, structural sequence, dust/noise and how services are isolated before strip-out begins.
What good looks like on a UK site
Never start soft strip without clarity on asbestos and structure. Sequence is a control. Name the site, the people at risk, and the sequence that keeps them safe. Generic paragraphs that could apply anywhere are the first thing a principal contractor rejects.
How SafeForJob helps
- Describe the job in plain English and get suggested activities, risks and method steps
- Edit every line before you download or issue
- Reuse a previous RAMS and catch old client or site names
- Attach or create COSHH assessments where hazardous substances appear
What this page is not
This page is not HSE approval, legal advice or a substitute for competent judgement. It helps you draft a clearer strip out method statement document for a named job. You remain responsible for reviewing and issuing it.
Related reading
See what a RAMS is, the free RAMS generator, and HSE guidance on managing risks.
Related pages
- GuidesWhat is a RAMS?RAMS means risk assessment and method statement — usually one site-specific pack for a construction or maintenance job. Practical UK guidance for contractors — with links to free tools.
- RAMS by tradeElectrical RAMSCreate a site-specific electrical RAMS online. Describe the job, review suggested risks like safe isolation and work at height, and download a professional PDF.
- RAMS by tradeHVAC RAMSCreate HVAC and refrigeration RAMS online: rooftop units, split systems, refrigerant recovery and brazing. Suggested risks and method steps you review before issue.
- RAMS by tradePlumbing RAMSCreate plumbing and heating RAMS online: boiler swaps, pipework, unvented cylinders and drain-downs. Suggested risks and method steps, reviewed by you.
- RAMS by tradeRoofing RAMSCreate a roofing RAMS online covering edge protection, fragile roofs, falling objects and weather. Suggested controls and method you review before issue.
- RAMS by tradeGroundworks RAMSCreate a groundworks or excavation RAMS online: buried services, trench collapse, plant movement and public interface. Review every suggestion before issue.
- RAMS by tradeFit-out RAMSCreate a fit-out or shopfitting RAMS online: partitions, ceilings, dust, occupied premises and out-of-hours work. Reviewed by you before issue.
- RAMS by tradeFire & security RAMSCreate RAMS for fire alarm, CCTV and access control installation: system isolations, ceiling work, occupied buildings. Review every suggestion before issue.
- RAMS by tradeScaffolding RAMSCreate scaffolding rams online for UK sites. Suggested risks and method steps matched to the job — you review every item before issue.
Questions
- Soft strip vs structural?
- Soft strip still needs surveys and exclusion; structural demolition needs specialist planning.
- Who holds the asbestos info?
- The dutyholder — get the survey before you write the method.
- Noise?
- Include Section 60/61 or client constraints where relevant.